Analysing factors affecting delays in Indian construction projects

机译:分析影响印度建设项目延误的因素

获取原文
获取原文并翻译 | 示例
           

摘要

Construction projects in India are experiencing widespread delays. Due to a dramatic shift in the capacity and volume of the Indian construction sector over the last decade, the need of a systematic analysis of the reasons of delays and developing a clear understanding among the industry professionals are highly crucial. Using a selected set of 45 attributes, this research first identified the key factors impacting delay in Indian construction industry and then established the relationship between the critical attributes for developing prediction models for assessing the impacts of these factors on delay. A questionnaire and personal interviews have formed the basis of this research. Factor analysis and regression modelling were used to examine the significance of the delay factors. From the factor analysis, most critical factors of construction delay were identified as (1) lack of commitment; (2) inefficient site management; (3) poor site coordination; (4) improper planning; (5) lack of clarity in project scope; (6) lack of communication; and (7) substandard contract. Regression model indicates slow decision from owner, poor labour productivity, architects' reluctance for change and rework due to mistakes in construction are the reasons that affect the overall delay of the project significantly. These findings are expected to be significant contributions to Indian construction industry in controlling the time overruns in construction contracts.
机译:印度的建筑项目遇到了普遍的延误。由于过去十年印度建筑业的能力和数量发生了巨大变化,因此需要系统分析延误的原因并在行业专业人士之间建立清晰的了解非常重要。本研究使用一组选定的45个属性,首先确定了影响印度建筑业延迟的关键因素,然后建立了关键属性之间的关系,以开发预测模型以评估这些因素对延迟的影响。调查表和个人访谈构成了这项研究的基础。因子分析和回归模型被用来检验延迟因子的重要性。从因素分析中,确定施工延误的最关键因素是:(1)缺乏承诺; (2)低效的现场管理; (3)现场协调性差; (四)规划不当; (5)项目范围不明确; (6)缺乏沟通; (七)不合格合同。回归模型表明业主的决策缓慢,劳动生产率低下,建筑师因施工错误而不愿进行更改和返工是显着影响项目总体延迟的原因。这些发现有望为控制建筑合同中的时间超支对印度建筑业做出重大贡献。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号