Time, cost and quality trade-off in project management: a case study

机译:项目管理中时间,成本和质量的权衡:一个案例研究

获取原文
获取原文并翻译 | 示例
       

摘要

In 1996, Babu and Suresh proposed a framework to study the trade-of t among time, cost and quality using three inter-related linear Programming models. This paper describes our attempt to apply the method to an actual cement factory construction project. The Purpose is to evaluate the practical applicability of the method by highlighting the managerial insights gained, as well as pointing out key problems and difficulties faced. As consequence, the paper helps practicing project engineers to have realistic expectations of the method. It also provides suggestions to overcome some practical problems if the method is to be applied in real industrial projects.
机译:1996年,Babu和Suresh提出了使用三个相互关联的线性规划模型研究时间,成本和质量之间的权衡的框架。本文介绍了我们将这种方法应用于实际水泥厂建设项目的尝试。目的是通过强调获得的管理见识以及指出面临的关键问题和困难,评估该方法的实际适用性。因此,本文有助于实践项目工程师对方法有现实的期望。如果要在实际的工业项目中使用该方法,它还提供了克服一些实际问题的建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号