The 280 MW Dhauliganga hydroelectric project on river Dhauliganga has been successfully implemented by NHPC during the period 2000-2005. The project located in remote location upstream of the town of Dharchula in Uttaranchal State is characterized by the difficult access conditions and unfavourable topography. In spite of many technical hurdles, the project has been successfully commissioned within the scheduled five year period and has started generation from September 2005 after commissioning of the 250 km long, 400 kV Dharchula-Bareilly transmission system executed by Power Grid Corporation of India. The project was financed by Japan Bank for International Cooperation (JBIC).
机译:NHPC已在2000-2005年期间成功实施了Dhauliganga河上的280 MW Dhauliganga水电项目。该项目位于Uttaranchal州Dharchula镇上游的偏远地区,其特点是交通条件困难和地形不利。尽管存在许多技术障碍,但该项目已在计划的五年内成功调试,并且在印度电网公司执行了250公里长,400 kV Dharchula-Bareilly输电系统调试后,于2005年9月开始发电。该项目由日本国际合作银行(JBIC)资助。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号