首页> 外文期刊>Hydro review >Reconfiguring Leads to Extend Stator Life
【24h】

Reconfiguring Leads to Extend Stator Life

机译:重新配置引线以延长定子寿命

获取原文
获取原文并翻译 | 示例
       

摘要

The Unit 6 generator (original Cana-dian Westinghouse) at the 450-MW (420 MVa) Isle-Maligne powerhouse began operating in 1923 and still has the original stator core and frame. The stator winding was replaced at least twice, and the last winding installed in 1988 started to show signs of degradation. Rio Tinto's maintenance team assigned this stator winding the second lowest reliability rating of its entire fleet (52 hydro units). In January 2014, the unit failed. Returning the unit to service required taking three coils out of the circuit, for a total of 12 coils cut out on a 360-coil winding. This breakdown was the fourth in four years; all the defective coils were located in the first four electrical positions close to the main connections. All showed a voltage to ground of 6.6 kV or higher. Partial discharges (PD) were very high and growing since 2010.
机译:450兆瓦(420兆瓦)Island-Maligne发电厂的6号机组发电机(原始的Canadian Westinghouse)于1923年开始运行,但仍具有原始的定子铁心和机架。定子绕组至少被更换了两次,最后一个绕组于1988年安装,开始显示出退化的迹象。力拓(Rio Tinto)的维护团队将此定子绕组的可靠性评为整个车队(52个水力发电机组)的第二低。 2014年1月,该部队失败了。要使设备恢复正常工作,需要从电路中取出三个线圈,以便在360线圈绕组中切出总共12个线圈。这是四年来的第四次故障。所有有缺陷的线圈都位于靠近主连接的前四个电气位置。全部显示对地电压为6.6 kV或更高。自2010年以来,局部放电(PD)很高,并且还在增加。

著录项

  • 来源
    《Hydro review》 |2016年第6期|90-91|共2页
  • 作者

    Denis Bussieres;

  • 作者单位

    Voith Hydro Inc.;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 01:03:34

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号