Plant Rolls In Replacement During Maintenance Outage

机译:在维护中断期间更换工厂设备

获取原文
获取原文并翻译 | 示例
       

摘要

Replacement of a piece of major equipment can take a big bite out of a powerplant's revenue, as the plant must be offline for the work to be done. But a Midwest utility completed demolition and replacement of one electrostatic precipitator in 10 weeks this spring and plans to repeat the operation next year. "The key driver for (replacing) the precipitators was the physical degradation from 35 years of operating experience," says Terry Ward, project manager for Cincinnati-based Cinergy Corp., the parent of PSI Energy Inc., which owns and operates Cayuga Generating Station, Cayuga, Ind. Ward anticipates stricter federal or state opacity regulations. The new precipitators remove 99% of partic-ulate matter and exceed state permit opacity requirements by 50%, he says.
机译:更换主要设备可能会大大消耗发电厂的收入,因为发电厂必须离线才能完成工作。但是,一家中西部的公用事业公司于今年春天在10周内完成了拆除和更换一台静电除尘器的计划,并计划明年再次运行。 “(取代)除尘器的主要驱动力是来自35年运营经验的物理退化,”总部位于辛辛那提的Cinergy Corp.(PSI Energy Inc.的母公司)的项目经理Terry Ward说。 Ward预期印第安纳州卡尤加市Station会制定更严格的联邦或州不透明规定。他说,新的除尘器去除了99%的颗粒物,并使州不透明度要求超出了50%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号