Development of the construction scheduling based on fuzzy discrete event simulation for a TFT-LCD plant

机译:TFT-LCD工厂基于模糊离散事件模拟的施工进度表的开发

获取原文
   

获取外文期刊封面封底 >>

       

摘要

For constructing a thin-film transistor liquid-crystal display (TFT-LCD) plant, a fuzzy-based scheduling method with discrete event simulation is developed. Apart from typical way for construction scheduling that only cope with quantitative data, fuzzy-based methods provide a proper mechanism for expressing planners’ linguistic terms to determine the level of factors that affect the construction scheduling planning. A construction planning process in modeling construction simulation system that applies the fuzzy reasoning and fuzzy ranking is presented here. The purpose of this study is expected to shorten the construction duration in a short computational time. An experimental example is to explore the validity of proposed method and to help TFT-LCD plant builders to manipulate their construction in quantitative and linguistic manners.
机译:为了构建薄膜晶体管液晶显示器(TFT-LCD)工厂,开发了一种基于模糊事件的离散事件模拟调度方法。除了仅能处理定量数据的典型施工进度计划方法外,基于模糊的方法还提供了一种表达规划人员语言术语,以确定影响施工进度计划因素的水平的适当机制。提出了在建筑施工仿真系统建模中应用模糊推理和模糊排序的施工规划过程。预期本研究的目的是在较短的计算时间内缩短施工时间。一个实验实例是探索所提方法的有效性,并帮助TFT-LCD工厂的建造者以定量和语言的方式操纵其建造过程。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号