GAO Finds Years Of Maintenance Delays For Carriers, Subs At Navy Shipyards

机译:高保人员在海军造船厂船只的维护延误多年来

获取原文
获取原文并翻译 | 示例
           

摘要

Maintenance work performed on aircraft carriers and submarines at four Navy shipyards is years behind schedule due to unplanned work and performance issues leading to negative impacts on military readiness, the Government Accountability Office (GAO) says in a new report. The shipyards completed 75 percent of the maintenance periods late for carriers and submarines between fiscal years 2015 and 2019, amounting to 7,424 days of delay, says the report, Actions Needed to Address the Main Factors Causing Maintenance Delays for Aircraft Carriers and Submarines (GAO-20-588). The seven thousand-plus days of delay amounts to more than 20 years.
机译:在四个海军造船厂的航空母舰和潜艇上进行的维护工作是由于无计划的工作和绩效问题导致导致对军事准备的负面影响,政府问责办公室(GAO)在一份新报告中表示,这是一年的时间。造船厂在2015年财政年度和2019年间的运营商和潜艇期间完成了75%的维护期间,延迟延迟的7,424天,所需的行动是为了解决航空母舰和潜艇的维护延误的主要因素所需的措施(高20-588)。七千多天的延迟金额超过20年。

著录项

  • 来源
    《Defense Daily》 |2020年第21期|5-6|共2页
  • 作者

    Cal Biesecker;

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号