Production and shipment planning for Project Based Enterprises: Exploiting learning-forgetting phenomena for sustainable assembly of Curtain Walls

机译:基于项目的企业的生产和装运计划:利用忘记学习的现象实现幕墙的可持续组装

获取原文
获取原文并翻译 | 示例
           

摘要

The production and shipment planning for Project Based Enterprises in the Curtain Walls industry is investigated in order to manage the typical trade-off between the assembly plant and the installation site requirements. Given the limited and intermittent nature of the production in large construction projects, empirical evidence is firstly provided about the impact of learning-forgetting phenomena on the assembly pace and the opportunity to include them into the planning process to generate more feasible plans and not to expose workers to excessive stress. A methodology is developed in order to assign proper values of learning-forgetting parameters to panels on the basis of features that, despite of the engineer-to-order nature of products, can survive in different projects. An optimisation model for mid-term production and shipment planning is then proposed, including learning-forgetting in cycle times, installation sequence-based restrictions, and container saturation. Costs due to idle time on the assembly line, setup, overtime, less than full load transports, and capital ones are then minimized by exploiting Constraint Programming and Large Neighborhood Search. The application of the model to an actual project has outlined its capability to support a company on both project decision-making and operational levels.
机译:对幕墙行业中基于项目的企业的生产和运输计划进行了调查,以管理组装厂和安装场所需求之间的典型权衡。鉴于大型建筑项目中生产的局限性和间歇性,首先提供经验证据,说明忘记学习现象对装配速度的影响,以及有机会将其纳入计划过程以生成更可行的计划而不暴露工人压力过大。开发了一种方法,以根据功能赋予面板适当的学习遗忘参数值,尽管产品具有按订单设计的性质,但可以在不同的项目中生存。然后,提出了用于中期生产和装运计划的优化模型,包括对周期时间的学习遗忘,基于安装顺序的限制以及容器饱和度。然后,通过使用约束编程和大型邻域搜索,将装配线上的闲置时间,设置,加班,少于满载运输的成本以及固定成本降至最低。该模型在实际项目中的应用概述了其在项目决策和运营水平上支持公司的能力。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号