Rotary piling ► lead times remain at seven weeks with no change reported. Precast piling ► lead times remain at four weeks with no change expected as workload and enquiry levels stay steady over the next six months. Concrete works ► lead times remain at 10 weeks as enquiry levels stay static. Concerns remain about the impact of Brexit on labour availability, but contractors do not anticipate an effect on lead times in the next six months. Structural steel frames ► lead times remain at 15 weeks; with workload and order levels unchanged they are forecast to stay steady for the next six months.
机译:旋转打桩►逾期持续时间仍然七周,没有任何变化报告。预制桩►交货时期仍然在四周内,由于工作量和查询水平在未来六个月内保持稳定,因此没有变化。混凝土作品►随着疑问水平保持静态,交货时期仍有10周。担心Brexit对劳动力可用性的影响,但承包商不会预计未来六个月内有关交货时间的影响。结构钢框架►延续时间仍留在15周;随着工作量和订单水平不变,预计将在未来六个月内保持稳定。

著录项

  • 来源
    《Building》 |2019年第18期|42-43|共2页
  • 作者

    Brian Moone;

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 22:31:17

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号