首页> 外文期刊>Building >LEAD TIMES JANUARY-MARCH 2019
【24h】

LEAD TIMES JANUARY-MARCH 2019

机译:领导时间2019年1月至3月

获取原文
获取原文并翻译 | 示例
       

摘要

Rotary piling ► lead times remain at seven weeks with no change reported. Precast piling ► lead times remain at four weeks with no change expected as workload and enquiry levels stay steady over the next six months. Concrete works ► lead times remain at 10 weeks as enquiry levels stay static. Concerns remain about the impact of Brexit on labour availability, but contractors do not anticipate an effect on lead times in the next six months. Structural steel frames ► lead times remain at 15 weeks; with workload and order levels unchanged they are forecast to stay steady for the next six months.
机译:旋转打桩►交货时间保持在七个星期,没有变化的报道。预制桩►交付周期为四个星期,由于工作量和咨询水平在接下来的六个月中保持稳定,预计交付周期不变。具体工作►询价水平保持不变,交货时间保持在10周。人们仍然担心英国退欧对劳动力供应的影响,但承包商预计未来六个月的交货时间不会受到影响。结构钢框架►交货时间保持在15周;在工作量和订单水平不变的情况下,预计在接下来的六个月中它们将保持稳定。

著录项

  • 来源
    《Building》 |2019年第18期|42-43|共2页
  • 作者

    Brian Moone;

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 04:22:48

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号