When the Building Team began the $60.7 million ren- ovation and modernization of the 1.4 million-sf Internal Revenue Service headquarters in Washington, it was obvious where to start. Sections of the building's slab-on-grade basement floor were sinking. The initial deflection, which involved an area of 15 by 25 feet, later spread to other sections of the 186,000-sf slab. The failures were caused by underground voids, ranging in depth from two inches to as much as three feet, that resulted from settlement and consolidation of the subsoil. The slab failure cracked underground piping, which had to be replaced. New underground storm, sewer, and subsoil drainage was installed.
机译:当建筑团队开始对华盛顿州国税局140万平方英尺的总部进行6070万美元的翻新和现代化改造时,显然该从哪里开始。该建筑物的地面层地下室地板的部分正在下沉。最初的变形涉及面积15乘25英尺,后来扩展到了186,000平方英尺的平板的其他部分。破坏是由于地下空隙的沉降和固结造成的,地下空隙的深度从两英寸到三英尺不等。平板故障使地下管道破裂,必须更换。安装了新的地下暴风雨,下水道和地下土壤排水系统。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号