以杭黄铁路跨浙江 S103省道四孔一联(60+100+100+60)m 大跨连续梁工程为例,根据现场施工条件,通过对连续梁施工三种方案的对比分析,确定了最佳方案,并提出了方案的管理措施,有效地控制了节点工期,节约了施工成本。%Taking four-hole one-league(60 + 100 + 100 + 60)m large-span continuous beam engineering of Hang-Huang railway crossing Zhejiang provincial highway S103 as an example,according to the site construction conditions,through comparatively analyzing here continuous beam con-struction schemes,the paper determines optimal scheme,and puts forward the scheme management measures. As a result,it effectively control joint construction duration and saves construction cost.