首页> 中文期刊> 《冶金动力》 >350 MW发电机组高炉煤气增压风机切换方式优化研究

350 MW发电机组高炉煤气增压风机切换方式优化研究

         

摘要

宝钢电厂4号机组配备3台BFG增压风机,与之配套的电动机为双速电动机,可以根据BFG用量的不同进行高、低速切换运行.在实际的切换运行中,对进口调节挡板的开度范围要求十分严格,仅在1个工况点下可以进行,因此,当需要增加BFG消耗量而将低速运行的风机切换高速运行时存在BFG的放散.通过试验数据和理论分析对切换方式进行优化,找到多种切换方案并达到保证压力的稳定、减少BFG放散,实现节能的目的.%The unit 4 of Baosteel Power Plant is equipped with 3 BFG booster fans with the ancillary motor using a two-speed motor, which can switch between high and low speed according to BFG amount. In actual switching operation, the range of entrance apron was strictly required with only one operating point. Therefore, BFG would be diffused when the booster fan was switched from low speed to high speed to increase BFG consumption. Through experiment and theoretical analysis the switching mode was optimized and a variety of switching programs was designed to maintain pressure stability, reduce BFG relief and save energy.