Mostaganem700套项目工期索赔案例分析

             

摘要

With a gradual expansion of CNQC in Algeria market, engineering claims for projects between clients and contractors increase. So a reduction in such losses proves to be of great importance and causes of non-self discrimination become a target profit maximization in project. This paper finds it important to seize claim opportunity, and makes a good analysis of claim evidence collection of data, claim analysis method, claim reports and the final negotiations with owner, etc. from Mostaganem700 sets of project period claim cases, and finally gains some experience of how to lessen claim cases in such projects.%随着我国承包商在阿尔及利亚市场的逐步扩大,承包商与业主之间的工程索赔案例不断增多.因此如何减少承包商非自身原因造成的损失,使目标利润最大化成为摆在项目面前的重要课题.引用Mostaganem700套项目部工期索赔成功的案例,通过抓住索赔机会、索赔证据资料的收集、索赔分析方法、索赔报告的编制以及最终与业主谈判等方面,归纳总结承包商在此项目索赔案例中的经验及教训,为相似工程提供借鉴.