Delay Causes Identified by Real Schedule Dispute Cases

机译:实际时间表争议案件确定的延误原因

获取原文
获取原文并翻译 | 示例

摘要

Public construction projects are often behind schedule due to various lands of uncertain, resulting in the conflicts between contract parties. Identifying the causes that affect the critical path and consequently the completion of a project is the most important aspect of delay analysis. Among the resolutions of solving these conflicts, litigation is the most costly and time consuming but it is often the final resolution. Previously, most studies tried to identify schedule delay causes by questionnaire survey. To some extent, the results by the questionnaire survey are subjective. This study focused on analyzing the contents of the Supreme Court verdicts in Taiwan about project schedule disputes in order to identify the main causes of schedule delay in construction projects. Through literature review and content analysis on 30 legal cases, this study identified that the major cause of schedule delay is "change order". Through the presentation of analysis results, this study clearly shows the causation of schedule delay in a project to provide a reference for preventing schedule disputes in the future.
机译:由于各种土地的不确定性,公共建设项目经常落后于进度,从而导致合同方之间的冲突。找出影响关键路径并因此导致项目完成的原因是延迟分析的最重要方面。在解决这些冲突的解决方案中,诉讼是最昂贵且最耗时的,但通常是最终解决方案。以前,大多数研究试图通过问卷调查来确定进度延迟的原因。问卷调查的结果在某种程度上是主观的。这项研究的重点是分析台湾最高法院关于项目进度争端的判决内容,以找出建设项目进度拖延的主要原因。通过对30项法律案件的文献回顾和内容分析,本研究确定了进度延迟的主要原因是“变更单”。通过分析结果的呈现,本研究清楚地表明了项目进度延迟的原因,为将来防止进度冲突提供了参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号