A Precedence Constraint Posting Approach for the RCPSP with Time Lags and Variable Durations

机译:具有时滞和可变时长的RCPSP的优先约束发布方法

获取原文
获取原文并翻译 | 示例

摘要

Resource Constrained Project Scheduling Problem is a very important problem in project management, manufacturing and resource optimization. We focus on a variant of RCPSP with time lags and variable activity durations. The solving approach is based on Precedence Constraint Posting that adds new precedence constraints to the original project graph so that all resource conflicts are solved and a consistent assignment of start times can be computed for whatever combination of activity durations. We propose a novel method for computing resource conflicts based on the minimum flow on the resource graph and we use it in an efficient complete search strategy. We experiment the approach on instances coming from the scheduling of parallel applications on multi processor systems on chip.
机译:资源受限的项目计划问题是项目管理,制造和资源优化中非常重要的问题。我们专注于具有时滞和可变活动持续时间的RCPSP变体。解决方法基于“优先约束发布”,该约束向原始项目图添加了新的优先约束,以便解决所有资源冲突,并且可以为活动持续时间的任何组合计算开始时间的一致分配。我们提出了一种基于资源图上的最小流量来计算资源冲突的新方法,并将其用于有效的完整搜索策略中。我们对实例的方法进行了实验,该实例来自片上多处理器系统上并行应用程序的调度。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号