首页> 外文会议>Pipelines 2008 >ANALYSIS OF DELAY CAUSES FOR PIPELINE PROJECTS IN SEWAGE SYSTEM: TAIWAN CASES
【24h】

ANALYSIS OF DELAY CAUSES FOR PIPELINE PROJECTS IN SEWAGE SYSTEM: TAIWAN CASES

机译:污水处理系统中管道项目的延迟原因分析:台湾案例

获取原文
获取原文并翻译 | 示例

摘要

In a sewage system development project, pipeline construction is the key work owing to pipeline construction shares high cost compared to other works. Furthermore, pipeline construction usually suffers unforeseen site conditions and results in tremendous delays. Identifying potential delay causes is the basis for resolving delay problems before they actually occur. As the budget of sewage systems is increased annually in Taiwan, identifying delay causes and preventing them from occurring are essential for successful sewage system construction projects. Through examining fifteen real cases and validating via a questionnaire survey, this study concluded that moving existed conduits later than planned schedule, unforeseen site conditions and delayed construction planning report approval are the top three significant causes for pipeline construction projects. Identifying the causes is valuable for reference to succeed in future similar projects.
机译:在污水系统开发项目中,管道建设是关键工作,因为与其他工程相比,管道建设的成本较高。此外,管道施工通常会遇到无法预料的现场条件,并导致极大的延误。找出潜在的延迟原因是在延迟问题实际发生之前解决它们的基础。由于台湾的排污系统预算每年都在增加,因此,找出延迟原因并防止其发生对于成功的排污系统建设项目至关重要。通过检查15个实际案例并通过问卷调查进行验证,该研究得出的结论是,将已存在的管道移至计划的时间表之后,无法预料的现场条件和延迟的施工计划报告批准是造成管道建设项目的三大主要原因。查明原因,对于将来在类似项目中取得成功具有参考价值。

著录项

  • 来源
    《Pipelines 2008》|2008年|p.1-10|共10页
  • 会议地点 Atlanta GA(US)
  • 作者

    Jyh-Bin Yang; rnPi-Yun Liao;

  • 作者单位

    Institute of Construction Management, Chunghua University, No.707, Sec.2, Wufu Rd., Hsinchu, 300, Taiwan TEL: +886 3 5186684 FAX: +886 3 5370517 e-mail: jyhbin@chu.edu.tw;

    rnNorthern Section, Division of Sewage Systems, Construction and Planning Agency. 5F, No. 60-2, Nanshan Rd., Jhonghe City, Taipei County 235, Taiwan TEL: +886 2 2404140 ext. 5501 FAX: +886 2 22400176 e-mail: n1lbu@cpami.gov.tw;

  • 会议组织
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 管道运输;
  • 关键词

    sewage system; pipeline project; case study; delay cause;

    机译:排污系统;管道工程;案例研究;延误原因;

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号