Tunneling through an operational oilfield and active faults on the ECIS Project, Los Angeles, CA, USA

机译:在美国加利福尼亚州洛杉矶的ECIS项目上穿越运营中的油田和活动断层进行隧道掘进

获取原文
获取原文并翻译 | 示例

摘要

A 2.5km (1.8 mile) long tunnel has been driven by a 4.7m (15.5ft) diameter EPB-TBM through sands and gravels of the Lakewood formation and very stiff massive clays and silts with minor occurrences of sand of the San Pedro formation. The Unit 1, western section, of the East Central Interceptor Sewer (ECIS) project tunnels beneath major utility lines with shallow cover, crosses the seismically active Newport-Inglewood Fault Zone beneath Baldwin Hills, and navigates through the Inglewood Oil Fields. The paper describes the hazard assessment and construction considerations of tunneling through faults and outlines risk avoidance planning to avoid abandoned oil wells. The paper then describes the performance of the TBM in the different ground conditions encountered, the forward probing method used to monitor for gas and the search for existing oil wells using a magnetometer both in a probe hole from the tunnel and also from the surface. Procedures are included describing the re-abandonment of an existing oil well discovered elsewhere on the project, and how successful implementation enabled the project to proceed safely.
机译:直径4.7m(15.5英尺)的EPB-TBM驱动了2.5公里(1.8英里)长的隧道,穿过莱克伍德地层的沙子和砾石以及非常坚硬的块状粘土和淤泥,而圣佩德罗地层的沙子则很少出现。东部中央拦截器下水道(ECIS)的第1单元西段隧道位于主要公用事业线下方,覆盖层较浅,穿过鲍德温山下的地震活跃的纽波特-英格伍德断层带,并穿越英格伍德油田。本文介绍了穿越断层隧道的危险性评估和施工注意事项,并概述了避免废弃油井的风险规避计划。然后,论文描述了TBM在遇到的不同地面条件下的性能,用于监测天然气的正向探测方法以及使用磁力计在隧道和地表探孔中搜索现有油井的方法。包括的程序描述了如何废弃在项目其他地方发现的现有油井,以及成功实施该项目如何使该项目安全进行。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号