Winnipeg's First Rapid Transit Corridor - Southwest Transitway

机译:温尼伯的第一个快速过境走廊 - 西南地区

获取原文

摘要

On April 8 2012, Winnipeg's first rapid transit facility opened for service. Constructed during 2009-2011, this initial stage of the Southwest Transitway includes a 3.6 km grade-separated busway, three highly-developed stations, a tunnel beneath the CN main line, a bridge over a major arterial roadway, and active transportation facilities. The newest buses in the fleet operate a network of 13 rapid transit routes over the transitway, offering one-seat trips for most passengers travelling between downtown and the growing southwest quadrant of the city. The rapid transit routes use the transitway in combination with other transit priority measures and real-time passenger information systems to provide service that is fast, reliable, comfortable, and convenient. Project funding approval in 2008 included a commitment to complete construction of this $138 million project by the end of 2011. With preliminary design only partially completed at the time of funding approval, a condensed schedule for final design and construction was developed. To achieve the construction target, the following major elements of the project were tendered separately: 1. 3.6 km of transitway runningway. 2. 2.5 km of land drainage sewer. 3. A 350 m transitway tunnel underpass of seven CN tracks. 4. A land drainage pump station for the tunnel underpass. 5. A100 m overpass of a major arterial road. 6. Three new transitway stations. 7. Overall project signage, streetscaping, aesthetics and landscaping. The technical paper discusses how the challenging features of site, location, and construction conditions influenced implementation strategy, and how a unique mix of design ingenuity, technology, and equipment were used to successfully complete the project faster, and safer.
机译:2012年4月8日,温尼伯的第一个为服务开放的快速运输设施。在2009 - 2011年期间建造的,西南地区的初始阶段包括3.6公里的分离的母线道,三个高度发达的车站,CN主线下方的隧道,一个主要的动脉道路,以及积极的运输设施。舰队中最新的公共汽车在Transitway上运营了13个快速交通路线的网络,为大多数乘客提供一个座位的旅行,以便在市中心和城市中越来越多的西南象限之间旅行。快速的交通路线使用Transitway与其他运输优先措施和实时乘客信息系统相结合,提供快速,可靠,舒适,方便的服务。 2008年项目筹资批准包括截至2011年底,致力于完成1.38亿美元的项目。在批准时仅部分完成,开发了最终设计和建设的凝结时间表。为了实现施工目标,项目的以下主要元素分别招标:1。距离Transitway Ringway 3.6公里。 2. 2.5公里的土地排水下水道。 3.七CN轨道的350米Transitway隧道地下通道。 4.隧道地下通道的陆地排水泵站。 5. A100M主要动脉道过桥。 6.三个新的Transitway站。 7.整体项目标牌,街头展示,美学和景观美化。技术论文讨论了现场,位置和施工条件如何影响实施策略的具体特征,以及如何更快地完成项目的独特组合,以及如何更快地完成项目,更安全。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号