LINDE FUSRAP SITE REMEDIATION, UTILITY TUNNEL REPLACEMENT, AND INDUSTRY OPERATIONS: A CASE STUDY OF CHALLENGES MET IN WESTERN NEW YORK

机译:Linde Fusrap网站修复,公用事业隧道更换和行业运营:纽约西部遇到挑战的案例研究

获取原文
获取外文期刊封面目录资料

摘要

Building 14 was a radiologically impacted Manhattan Engineer District-era (MED) structure at the Linde Formerly Utilized Site Remedial Action Program (FUSRAP) remediation site in Tonawanda, New York that required dismantlement in 2004. Remedial action at the Linde Site required simultaneous radioactive contamination cleanup, active industrial facility infrastructure relocation and uninterrupted facility operations. The challenge was to design and construct a replacement subsurface utility tunnel, relocate numerous active utilities, and remove all radioactive contamination within the new tunnel’s footprint within 16 months to allow Building 14 dismantlement to start on time. The U.S. Army Corps of Engineers – Buffalo District (USACE) and Shaw Environmental, Inc. (Shaw) worked in close cooperation with the facility owner to design and execute the work. Meeting the challenge involved design and construction of a new structure, a large open excavation between closely spaced steel and masonry buildings, and of several utility systems including high-pressure steam, high voltage electric, and fiber optic communications concurrent with removal of several thousand tons of uranium-238 (U-238), radium-226 (Ra-226), and thorium-230 (Th-230) impacted material. Design started in February 2003 and construction was completed in June 2004 to meet the Building 14 dismantlement start date.
机译:14楼是林德以前利用的曼哈顿工程师区时代(MED)结构,以前在纽约州的林德兰达州林德省的林德卫报案例(Fusrap)修复现场,在2004年要求拆除。Linde网站的补救行动要求同时放射性污染清理,主动工业设施基础设施搬迁和不间断设施运营。面临的挑战是设计和构建替代地下的外表隧道,重新安置众多积极的实用程序,并在16个月内删除新隧道的足迹内的所有放射性污染,以便建立14个拆除以准时开始。美国军队工程师 - 布法罗区(USACE)和Shaw环境,Inc。(Shaw)与设施所有者的密切合作致力于设计和执行工作。迎接挑战涉及新结构的设计和建设,在紧密间隔的钢和砖石建筑之间进行大开放的开挖,以及包括高压蒸汽,高电压电动和光纤通信的几个公用事业系统,并拆除几千吨铀-238(U-238),镭-226(RA-226)和钍-230(TH-230)受冲击材料。设计于2003年2月开始,建设于2004年6月完成,以满足建筑物14拆迁开始日期。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号