首页> 外文会议>Rapid Excavation and Tunneling Conference >DEEP SHAFT CONSTRUCTION IN UNCONSOLIDATED MATERIAL AND WATER-BEARING FORMATIONS
【24h】

DEEP SHAFT CONSTRUCTION IN UNCONSOLIDATED MATERIAL AND WATER-BEARING FORMATIONS

机译:未覆盖材料和含水结构的深轴结构

获取原文

摘要

The design/build of two adjacent vertical mine shafts in difficult ground conditions at a mining complex in the mid-western United States required innovative construction techniques. Construction of the 267-m-deep Service Shaft required full depth dewatering wells and ground freezing. Blind drilling was utilized to excavate the 257-m-deep Production Shaft and it was finished with a steel/concrete composite liner that was floated into place. An equally unique component of the installation included supplying a high capacity vertical conveyor system, featuring a 273-m-lift. Other components of the project include the mine level development, as well as the design and installation of three hoisting systems, including a 45-ton capacity men/materials hoisting system.
机译:在美国中西部的采矿综合体中,两个相邻的垂直矿井的设计/建造在美国中西部的矿区需要创新的施工技术。建设267米深施工轴,需要全深度脱水井和地面冻结。盲钻被利用挖掘257-M-深的生产轴,并用漂浮到位的钢/混凝土复合材料衬里完成。安装的同样独特的组件包括提供高容量立式输送系统,具有273米升力。该项目的其他组件包括矿山水平开发,以及三种提升系统的设计和安装,包括45吨容量的男性/材料吊装系统。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号