Field measurement and analysis on the prestress loss of a long-span PC box Girder Bridge

机译:长跨度PC箱梁桥预应力损失的现场测量与分析

获取原文

摘要

The crack and large deflection of long-span PC box Girder Bridge is common in their service stage. The lower estimation for the loss of prestress is one of possible reasons. Combined with a long-span prestressed concrete box girder bridges, the loss of longitudinal and vertical prestress of a long-span PC box girder bridge is measured during the construction and service stage. Based on the measured results, the loss of the longitudinal and vertical prestress of the long-span PC box girder bridge is analyzed by GA-ANN method and the code of JTG D62-2004, respectively. The results demonstrate that the instantaneous loss of the longitudinal prestress is more than 40% of the designed value, and the total loss of the vertical prestress is about 40% more than the designed one as well. The value of the prestress loss is much higher than the expected one of the design. The reason lies in the inappropriate construction technology, such as not tension the prestress to the designed value, tension at an early age, and excessive different of the tube wobble and so on. Therefore, the engineering quality control must be strengthened during the construction stage of the long-span PC box girder bridge for avoiding excessive prestress loss.
机译:长跨度PC箱梁桥的裂缝和大偏转在其服务阶段很常见。预应力损失的估计估计是可能的原因之一。结合长跨度预应力混凝土箱梁桥梁,在建筑和服务阶段测量了长跨度PC箱梁桥的纵向和垂直预应力的损失。基于测量结果,分别通过GA-ANN方法和JTG D62-2004的代码分析了长跨度PC箱梁梁桥的纵向和垂直预应力的损失。结果表明,纵向预应力的瞬时损失是40%以上的设计值,并且垂直预应力的总损失也比设计的更高约40%。预应力损失的价值远高于预期的设计。原因在于不适当的施工技术,如不张力预应力到设计的价值,张力在早期的张力,并过度不同的管道摆动等等。因此,在长跨度PC箱梁梁桥梁施工阶段,必须加强工程质量控制,以避免过度预损失。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号