首页> 外文会议>Water Environment Federation Technical Exhibition and Conference >The Venice Dual Force Main: Ensuring Resiliency through Redundancy in a Historically Large Scale Microtunneling Project
【24h】

The Venice Dual Force Main: Ensuring Resiliency through Redundancy in a Historically Large Scale Microtunneling Project

机译:威尼斯双主力:在一个历史上规模巨大的微型隧道项目中,通过冗余确保弹性

获取原文
获取外文期刊封面目录资料

摘要

This paper presents resiliency through redundancy construction management considerations and techniques that were used in the Venice Dual Force Main project. The project's intent is to construct a second force main sewer to operate in tandem with the existing force main sewer for the purpose of fulfilling the three key objectives, (1) The new force main will operate as a parallel system in conjunction with the existing 48" force main to meet the existing Peak wet weather Flow demands experienced at Venice Pumping Plant. (2) Add operational flexibility and reliability. (3) Allow isolation of either force main during low flow conditions to perform necessary cleaning and maintenance. During the heavy storms in 1995, Venice Pumping Plant VPP experienced a tremendous amount of peak wet weather flow (PWWF) that was contributed by stormwater infiltration in the sewershed. At times, the PWWF exceeded the maximum capacity. As a result, sewage rose in the plant's equalization wet well, reaching a critical level. With this potential serious public health and environmental risk, the City of Los Angeles recognized the need to increase the output capacity in order to be resilient to the existing infrastructure. With this project, the current and proposed capacity concluded that the addition of this 54" force main sewer will increase the current capacity from 44,000 gpm to 57,000 gpm, with four pumps operating and one pump in standby mode. With the current PWWF of 45,000 gpm, the combined 54-inch/48-inch dual force mains can safely handle, in tandem, this capacity with three pumps in service and two pumps in standby mode. The project is in the City of Los Angeles in the communities of Venice and Playa Del Rey, which constructs approximately 10,800 feet of a new 54-inch-diameter force main sewer in the City of Los Angeles, California. The construction is being performed under a major 4-lane road in the neighboring City of Marina del Rey, adjacent to multi-million dollar residences and below the water table and a dense layer of existing utilities and then crosses under the Marina Entrance Channel and Ballona Creek. From there, the alignment continues south along Pacific Avenue and Vista del Mar and connects to the junction structure of the Coastal Interceptor Sewer Venice Dual Force Main (CIS) and North Outfall Sewer (NOS) next to high visibility beach areas. To manage this complex micro tunneling project in both politically and environmentally sensitive area, a team of Project, Engineering, Construction, and Public Outreach management were organized to plan the tasks of design, constructability review, geotechnical investigations, environmental assessment, right of way assessment, permitting evaluations, multiple solicitation/bid and award stages, and through construction and closeout. The trenchless construction method, which utilizes hydraulic jacks to push pipes through the ground behind a remotely operated Micro-tunnel boring machine (MTBM). Drive lengths are generally limited to about 1,000 feet, depending upon ground conditions and pipe size; but intermediate jacking stations can be used to extend the drive length. Unlike conventional trenching techniques that require excavation for the entire length of the pipeline, excavation for tunneling is limited to the endpoints of each drive at designated launching (jacking) and receiving pits. The launching pit contains the hydraulic jacks used to push the pipes, and the receiving pit is used to recover the TBM at the end of each drive. Tunneling can proceed intermittently; although, it is often necessary to proceed continuously, particularly on long drives through sticky soils, to prevent the pipe from getting stuck short of the receiving pit. Tunnel advance rates are typically between 30 and 50 feet per 8-hour work shift, depending on soil conditions and pipe size. The tunnel face is supported by a thick liquid ("slurry"), which is a mixture of the excavated soil ("muck") and bentonite (a natural clay mineral). Keeping the slurry pressurized in a closed chamber behind the cutter-head of the TBM prevents groundwater and excess soil material from entering the TBM. During construction, the Construction Management Team implemented processes to monitor and report on a daily basis any potential problems, including soil-related issues (i.e., heave, settlement, slurry consistency) and tunneling machine issues (i.e., misalignment, steering or stoppage). Other than the normal construction management factors, additional processes were implemented along with a comprehensive public outreach program to mitigate public nuisances and complaints (i.e., noise and vibration problems and traffic flow). This paper will provide guidance and lessons learned for planners, engineers, designers, construction managers on planning, designing, and construction management of large scale microtunneling projects to ensure sustainability and redundancy to their existing infrastructure.
机译:本文通过冗余施工管理考虑因素和技术,介绍了威尼斯双力主项目中使用的弹性。该项目的目的是建造第二条警队主下水道,与现有警队主下水道同步运行,以实现三个关键目标,(1)新的干管将与现有的48”干管一起作为一个平行系统运行,以满足威尼斯泵站现有的峰值湿天气流量需求。(2)增加操作灵活性和可靠性。(3)允许在低流量条件下隔离任何一个主力管,以进行必要的清洁和维护。在1995年的强风暴期间,威尼斯水泵厂VPP经历了大量的峰值湿天气流量(PWWF),这是由下水道中的雨水渗透造成的。有时,PWWF超过最大容量。结果,污水在工厂的湿井中上升,达到了临界水平。鉴于这一潜在的严重公共健康和环境风险,洛杉矶市认识到需要提高产能,以适应现有基础设施。有了这个项目,当前和拟议产能的结论是“force main sewer将目前的污水处理能力从44000 gpm增加到57000 gpm,四台泵运行,一台泵处于备用模式。当前的PWWF为45000 gpm,组合的54英寸/48英寸双压力干管可以在三台泵运行和两台泵处于备用模式的情况下安全地串联处理该容量。该项目位于洛杉矶市的威尼斯a社区nd Playa Del Rey,在加利福尼亚州洛杉矶市建造了一条直径约为10800英尺的新的54英寸force主下水道。该工程是在邻近城市马里纳·德雷的一条主要四车道道路下进行的,毗邻价值数百万美元的住宅,地下水位和一层密集的现有公用设施下方,然后穿过马里纳入口通道和巴洛纳溪。从那里开始,路线沿着太平洋大道和Vista del Mar向南延伸,并连接到高能见度海滩区域旁边的沿海截流下水道威尼斯双力干管(CIS)和北部排水下水道(NOS)的连接结构。为了在政治和环境敏感区域管理这一复杂的微型隧道项目,组织了一个项目、工程、施工和公共外联管理团队,以规划设计、可施工性审查、岩土工程勘察、环境评估、通行权评估、许可证评估、多个招标/投标和授予阶段的任务,通过施工和收尾。非开挖施工方法,利用液压千斤顶在远程操作的微型隧道掘进机(MTBM)后面推动管道穿过地面。根据地面条件和管道尺寸,驱动长度通常限制在1000英尺左右;但中间顶升站可用于延长驱动长度。与需要对整个管道长度进行开挖的传统挖沟技术不同,隧道开挖仅限于指定发射(顶升)和接收坑处每个驱动的端点。下水坑包含用于推动管道的液压千斤顶,接收坑用于在每次掘进结束时回收TBM。隧道可以间歇性进行;尽管如此,通常有必要连续进行,尤其是在粘性土壤中的长距离驱动上,以防止管道卡在接收坑附近。隧道掘进速度通常为每8小时工作班30至50英尺,具体取决于土壤条件和管道尺寸。隧道表面由一种粘稠液体(“泥浆”)支撑,该液体是开挖土壤(“淤泥”)和膨润土(一种天然粘土矿物)的混合物。在TBM刀盘后面的封闭室内保持泥浆加压,防止地下水和多余的土壤材料进入TBM。在施工期间,施工管理团队实施流程,每天监测和报告任何潜在问题,包括土壤相关问题(即隆起、沉降、泥浆稠度)和隧道掘进机问题(即错位、转向或停止)。除了正常的施工管理因素外,还实施了额外的程序,以及一项全面的公众宣传计划,以减轻公众的滋扰和投诉(即噪音和振动问题以及交通流量)。本文将为规划师、工程师、设计师、施工经理提供大型微型隧道工程规划、设计和施工管理方面的指导和经验教训,以确保其现有基础设施的可持续性和冗余性。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号