Production Rate Regression Model of Railway Construction Project based on Grid

机译:基于网格的铁路建设项目生产率回归模型

获取原文

摘要

Project schedule has been regarded as the core work of the project management. Scheduling and using the project schedule scientifically and reasonably is the key to ensure the organization work of construction project orderly. In this paper, the time-location-based division method of influencing factors has been developed according to their time-spatial varying features. The paper has collected the actual construction progress data and taken use of multiple linear regression analysis determining the incidence relation between the production rates and influence factors. Then the regression model with varying production rates based on grids could be developed. Finally, the practical schedule data of railway Wu Caiwan-Jiang Junmiao sectional subgrade engineering has been utilized to verify the validity of the model.
机译:项目时间表被视为项目管理的核心工作。在科学合理地调度和使用项目时间表是确保有序建设项目组织工作的关键。在本文中,根据其时间空间不同的特征开发了基于时间位置的影响因素的方法。本文收集了实际施工进度数据,采用了多元线性回归分析,确定生产率与影响因素之间的发病关系。然后可以开发基于网格的不同生产率的回归模型。最后,已经利用了铁路武才湾 - 江俊义分区路基工程的实用进度数据来验证模型的有效性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号