首页> 外文会议>International Conference on Recent Advances in Rock Engineering >Advanced vibration management to improve productivity and optimize cost for excavation of iron ore: A case study
【24h】

Advanced vibration management to improve productivity and optimize cost for excavation of iron ore: A case study

机译:先进的振动管理,提高生产力和优化铁矿石挖掘成本:案例研究

获取原文

摘要

A major concern in deep hole blasting in open cast mining operation is the excessive generation of ground vibration and their effect on nearby industrial infrastructures and residential dwellings of local community. A poor blast output results in lower productivity of excavators which has a paramount adverse effect on overall cost structure of mining operation. Drilling and blasting cost comprises a significant part of the overall operations and maintenance cost in an open cast excavation process. The paper describes the result of systematic study carried out to manage ground vibration and blast output parameters at Joda East Iron Mine, which has an annual excavation of 12.5 MT (FY 16). The study involved detonation of multiple blast holes to determine the effective charge weight per delay and generate site specific empirical equations and constants. A further detailed study was then carried out using stastical - simulation technique to specify the blast designs and delay pattern for reducing the blasted mean particle size of rock strata which has a compressive and tensile strength of 145.3 MPa and 13.6 MPa respectively. The average density of rock is 3500 kg/m3. A correlation was then established between drill feed pressure and rock hardness to optimize the explosive charge per delay. The peak particle velocity data were recorded at point of interest. This data was subsequently analyzed for developing the limits of vibration. A correlation model was then established between predicted and actual vibration at point of interest. The result showed approximately 90% accuracy between these parameters. Electronic delay detonators were introduced for controlling the blast design parameters with variation in the explosive charging methods. A comparative study was then simulated for measuring the cost effectiveness in overall mine to mill operation which resulted in a significant amount of cost saving over the entire value chain. Paper also represented the overall range of cost and blast output parameters in different rock strata of iron ore and has several recommendations for enhancing blast output, which have suitable benefits in mining industry.
机译:开放式铸造运营中深孔爆破的主要问题是过度产生的地面振动及其对地方社区附近的工业基础设施和住宅的影响。一种较差的爆炸输出导致挖掘机的生产率降低,这对采矿操作的整体成本结构具有倾向的不利影响。钻孔和爆破成本包括开放式挖掘过程中整体运营和维护成本的重要部分。本文描述了在焦田东铁矿管理地面振动和爆破输出参数的系统研究结果,该挖掘矿拥有12.5吨(16岁)的年开挖。该研究涉及爆炸多个鼓风孔,以确定每个延迟的有效电量,并产生特定的实验性方程和常数。然后使用体制 - 模拟技术进行进一步的详细研究,以指定用于减少岩石地层的爆破平均粒径的爆破设计和延迟模式,其分别具有145.3MPa和13.6MPa的压缩和拉伸强度。岩石的平均密度为3500 kg / m3。然后在钻馈压力和岩石硬度之间建立相关性,以优化每个延迟的爆炸性电荷。在兴趣点记录峰值粒子速度数据。随后分析该数据以发展振动的限制。然后在兴趣点预测和实际振动之间建立相关模型。结果在这些参数之间显示了大约90%的精度。引入了电子延迟雷管,用于控制爆炸设计参数,具有爆炸性充电方法的变化。然后模拟比较研究,用于测量整个矿井的成本效益,以磨机运行,导致整个价值链上的大量成本节省。纸张还代表了铁矿石不同岩石地层中的成本和爆破输出参数的总体范围,并有几项提高爆炸产量的建议,在采矿业具有适当的益处。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号