CFG pile + vibro-replacement stone column pile to treat soil liquefaction on power plant

机译:CFG桩+振动置换石柱桩,用于治疗发电厂的土壤液化

获取原文

摘要

Silt foundation of the power plant in Shangqiu area was select as the research object, to verification the effect of foundation treatment for CFG pile and CFG pile + vibro-replacement stone column pile methods. The results showed that: bearing capacity of the foundation was improved after the CFG pile or CFG + vibro-replacement stone column composite foundation, the characteristic value of subsoil bearing capacity increase from 111kPa to 256kPa or 332kPa, respectively. The value of bearing capacity increment after treatment by the two methods is in the same order of magnitude. However, the liquefaction of silt foundation can be eliminated by treatment with CFG pile + vibro-replacement stone column pile. It is concluded that the value of bearing capacity after treatment by the two methods is both meet the requirement of the auxiliary building in power plant, and which one is suitable is based on whether the building is sensitive to liquefaction.
机译:上调地区电厂的淤泥基础是选择的研究对象,验证基础处理对CFG桩和CFG桩的效果+振动置换石柱桩方法。结果表明:CFG桩或CFG + Vibro-replacement石柱复合地基后,基础承载能力得到改善,骨质轴承能力的特征值分别从111kPa增加到256kpa或332kpa。通过两种方法处理后承载能量增量的值呈相同的数量级。然而,通过用CFG桩+振动置换石柱桩处理可以消除淤泥基础的液化。结论是,通过两种方法处理后承载能力的值均符合发电厂辅助建筑物的要求,其中一个是合适的,基于该建筑是否对液化敏感。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号