【24h】

Schedule-cost Joint Management of Thermal Power Construction Project Based on Improved Earned Value Method

机译:基于改进赚取的价值法的热电力建设项目的进度 - 成本联合管理

获取原文

摘要

The risk of schedule and cost is the core part in the thermal power construction projects, while the traditional earned value method often ignores the existence of the risk in the schedule and cost analysis. This paper presents an improved earned value analysis method considering risk factors. In the method, the schedule and cost performance indicator is fuzzed based on trapezoidal fuzzy number, then introduces risk level coefficient to construct fuzzy earned value method considering risk factors based on the cut, and realize the integration of risk management and schedule cost analysis. Finally, one thermal power project is taken as an example to testify the practicability and validity of the improved model.
机译:计划和成本的风险是热电建设项目中的核心部分,而传统的赚取的价值方法往往忽视了日本和成本分析中存在风险的存在。本文提出了考虑风险因素的改进的赚取价值分析方法。在该方法中,基于梯形模糊数来模糊的时间表和成本性能指标,然后介绍风险级系数,以考虑基于切割的风险因素的模糊赚取的价值方法,实现风险管理和调度成本分析的整合。最后,将一个热力电源项目作为示例,以证明改进模型的实用性和有效性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号