IN-SITU GEOTECHNICAL INVESTIGATION OF A CONFINED SEDIMENT DISPOSAL FACILITY, SYDNEY HARBOUR, NOVA SCOTIA

机译:原位岩土工程调查狭窄沉积物处置设施,悉尼港,新斯科舍省

获取原文

摘要

During the winter of 2011-2012, 4.2 million cubic meters of material was dredged from the navigation channel of Sydney Harbour. 3.8 million Cubic meters of this sediment was used to construct a Confined Disposal Facility (CDF) on the western shore of Sydney Harbour's South Arm. In October 2012 and July 2013, two surveys utilizing the portable free-fall penetrometer Nimrod were undertaken to investigate the sediment dynamics of the Harbour and evaluate the stability of recently deposited dredged sediments at the CDF and throughout the channel. The results of these two surveys showed a consistent trend of consolidation of the dredge material and a decrease in the thickness of the potentially mobile sediment top layers. In addition to the marked decrease in the top layer thickness (TLT), slumping of newly deposited dredged sediment from the near-shore, toward the mid-channel, was observed.
机译:2011 - 2012年冬季,从悉尼港的导航渠道脱离了420万立方米。 380万立方米的这种沉积物被用来在悉尼港南臂的西岸建造一个受限的处置设施(CDF)。 2012年10月和2013年7月,采用便携式自由落体污水仪Nimrod的两次调查进行了调查港口的沉积动力学,并评估最近沉积在CDF和整个通道的疏浚沉积物的稳定性。这两种调查的结果表明,疏浚材料的整合趋势和潜在移动沉积物顶层厚度的减少。除了顶层厚度(TLT)的显着降低之外,观察到从近岸的新沉积的疏浚沉积物朝向中间通道的坍塌。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号