MODERN LOW-NOX FIRING SYSTEM UPGRADE TO ACHIEVE IMPROVED RELIABILITY AND LOWER NOX EMISSIONS

机译:现代低Nox发射系统升级以实现改善的可靠性和较低的NOx排放

获取原文

摘要

Steinmuller Engineering was contracted by ESKOM to improve the firing system at Camden Power Station. Camden PS is a coal fired plant consisting of eight 200 MWe units. The plant was originally designed for a service life of 40 years and was commissioned during the period 1966-69. Due to surplus capacity the plant was shut down and preserved during the period 1988-90. Due to increasing power demand it was decided to reactivate the plant. The first unit was re-commissioned and synchronized in 2005 and the entire return to service project was completed in 2010. The Camden boilers are front wall fired and each unit is equipped with 20 burners arranged in five rows. Each row of burners is installed in a common windbox. The motivation behind this project was mainly driven by the need to improve boiler reliability. The previously installed combustion system was prone to severe burner related operational problems leading to unplanned boiler outages. To address the abovementioned challenges the existing burners were replaced with modern Low-NOX burners, which are characterised by very precise ignition and flame control. Simultaneously the new burners reduced the NOX emissions. Steinmuller Engineering implemented a solution with minimal impact on the existing system, in terms of scope of required modifications to the existing plant. The engineering phase to customize the design to meet the specific requirements of the boiler is completed. In 2015, the manufacturing and installation, executed by local companies,was completed for the first two units. The remaining six units will be retrofitted in the next years during scheduled plant outages. The installed Low-NOX burners are of Steinmuller Engineering’s latest generation bituminous coal burners.
机译:Steinmuller工程是由ESKOM合同,以改善卡姆登发电站发射系统。卡姆登PS是燃煤电厂由八个200兆瓦机组。该工厂最初设计的40年使用寿命期间1966-69委托。由于产能过剩的工厂被关闭,在此期间1988-90保存。由于电力需求的增加,决定重新激活植物。第一单元是重新委托并于2005年同步和整个返回到服务项目在2010年卡姆登锅炉完成是前壁烧制,并且每个单元配备有配置在五排20级的燃烧器。燃烧器的每一行被安装在一个共同的风箱。这个项目背后的动机主要是由需要提高锅炉的可靠性驱动。以前安装的燃烧系统是容易导致非计划停运锅炉燃烧器的严重有关操作问题。为了解决现有的燃烧器被替换为现代低NOx燃烧器,其特点是非常精确的点火和火焰控制上述挑战。同时新的刻录机降低NOx排放。 Steinmuller工程实现与现有系统的影响最小,在需要修改现有的工厂范围方面的解决方案。该工程阶段定制设计,满足锅炉的具体要求完成。在2015年,制造和安装,由当地公司执行,完成前两个单位。其余六个单位将在未来几年中,计划工厂停产进行改装。安装的低NOx燃烧器是Steinmuller工程的最新一代烟煤燃烧器。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号