After purchasing the Proctor Hydroelectric Station in Proctor, Vermont, in 2011, Green Mountain Power (GMP) undertook a multi-year, phased approach to redevelop nearly all components of the station. Upgrades included reconfiguring and streamlining the intake; replacing a 9-foot-diameter penstock; removing two surge tanks; replacing three vertical turbines installed in 1905 with new, vertical-axis, Francis units; rewinding and restoring the generator of a vertical Francis unit installed in 1926; replacing electrical power and control systems; constructing an access bridge to the power station; and other modifications to improve generation, operation, and safety of the station. Since completion of the project in 2015, the station’s generation capacity has increased from 3 megawatts (MW) to more than 10.23 MW, and it is now the largest of GMP’s 32 hydroelectric generating facilities. This paper describes the redevelopment of an historic, deteriorated, and nearly obsolete project into a modern, reliable, and safe facility and discusses the challenges encountered during the design, permitting, and construction phases of the project.
机译:在购买Proctor的Proctor水力发电站之后,2011年,绿山力(GMP)进行了一个多年的分阶段方法来重新开发车站的所有组件。升级包括重新配置和简化摄入;更换一个9英尺直径的乒乓球;去除两个浪涌坦克;用新的,垂直轴,弗朗西斯单位代替1905年安装的三个垂直涡轮机;倒带和恢复1926年安装的垂直弗朗西斯单元的发电机;更换电力和控制系统;构建到电站的接入桥;和其他改进站的发电,操作和安全的修改。自2015年完成项目以来,该站的发电能力从3兆瓦(MW)增加到10.23兆瓦,现在是GMP 32水电发电设施中最大的。本文介绍了历史,恶化,几乎过时的项目进入现代,可靠和安全的设施,并讨论了项目的设计,允许和建设阶段遇到的挑战。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号