The Application of Compaction Sand Pile in the Yellow River-Crossing Project for South-to-North Water Diversion

机译:压实砂桩在黄河交叉工程中的应用南北面分水

获取原文

摘要

In the construction of Yellow River-Crossing Project for the Middle Route of the South-to-North Water Transfer, the silt, silty sand and fine sand widely exist in the foundation, that it need to be processed in the region where the possibility of sand liquefaction because of the low bearing capacity. We had a detailed study and experiment for the sand compaction pile of the axis and the outside of the channel, and determined the compactness of pile body, pile length and the construction technology through the test. We also debugged the concrete construction parameters such as the amount of filling sand and stone, hoisting height and speed, extrusion times and so on. For these experiments, we attained the purpose of increasing the relative density, preventing sandy soil liquefaction, improving the shear strength of the foundation soil and the bearing capacity of the foundation, so as to reduce the foundation settlement.
机译:在南北水路中间路线建设中,淤泥,粉砂和细沙在基础上广泛存在,需要在可能的可能性中加工由于承载能力低,液化液化。我们对轴的轴和外侧的砂压实桩进行了详细的研究和实验,并通过测试确定了桩体,桩长和施工技术的紧凑性。我们还调试混凝土施工参数,如灌装砂和石材,升降高度和速度,挤出时间等。对于这些实验,我们达到了增加相对密度,防止砂土液化,提高基础土壤剪切强度和基础承载力的目的,以减少基础沉降。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号