Temperature Control Method and Application for Fast Pouring Concrete Dam

机译:快速浇筑混凝土坝的温度控制方法及应用

获取原文

摘要

In recent years, several concrete dams try a fast pouring method. To achieve the fast construction aim, thicker pouring layer or shorter interval is adopted. The fast pouring idea is introduced and then the layer thickness and pouring interval are analyzed. To reveal the temperature and stress safety of the fast pouring dam, numerical simulation is applied in a high roller compacted concrete dam. The layer of 3m, 4.5m and 6m are simulated and analyzed separately. The main disadvantage of thicker layer is more temperature difference between concrete inner and surface which will cause more surface tensile stress in early age. But the shortcoming can be overcome by reasonable combination of pouring temperature, pipe cooling and surface insulation. The temperature control measure and the corresponding norm have been applied in the actual construction. In the construction of past 2 years, nearly no crack appeared in the fast pouring concrete dam.
机译:近年来,几个混凝土坝尝试了快速浇注方法。为了实现快速施工目的,采用较厚的浇注层或更短的间隔。介绍了快速倾倒的思想,然后分析了层厚度和浇注间隔。为了揭示快速倾倒坝的温度和应力安全性,高辊压实混凝土坝中施加数值模拟。分别模拟3M,4.5M和6M的层。较厚层的主要缺点在于混凝土内部和表面之间的温差更温差,这将在休眠中引起更高的表面拉伸应力。但是,通过合理的浇注温度,管道冷却和表面绝缘材料可以克服缺点。温度控制措施和相应的规范已应用于实际结构。在过去2年的建设中,快速浇筑混凝土大坝几乎没有裂缝。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号