Study on the treatment and settlement monitoring technology of passenger dedicated line collapsible loess foundation

机译:乘客专用线路折叠黄土基础的处理与定居监测技术研究

获取原文

摘要

By the engineering background of Datong-Xian Passenger Dedicated Railway Line passing through the collapsible loess area, four representative test sections such as roadbed-bridge transition section, roadbed-culvert transition section, ordinary and special embankment section was selected. Different pile parameter and pile plane layout and subgrade filling measure has been taken according to the different test sections. At the same time, the correspondence of settlement monitoring project was carried out. After the long time monitoring, by the hyperbolic curve and logarithmic method predicting, the long-term settlement has been predicted. The monitoring results and the curve fitting shows that the settlement and the foundation treatment schemes with subgrade filling measurement meet the design requirement also provided reference and reference for other engineering.
机译:由大同县客运专用铁路线的工程背景通过可折叠黄土地区,选择了四个代表性测试部分,如道路 - 桥式过渡部分,路基涵洞转换部分,普通和特殊路堤部分。根据不同的测试部分,采取了不同的绒毛参数和桩平面布局和路基填充度量。与此同时,进行了结算监测项目的对应。经过长时间的监测,通过双曲线曲线和对数方法预测,已经预测了长期结算。监测结果和曲线配件表明,具有路基填充测量的沉降和基础处理方案符合设计要求,还为其他工程提供了参考和参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号