首页> 外文会议>Membrane technology >Design and First-Year Operation of the 50 mgd Membrane Treatment Facility at Gwinnett County, Georgia
【24h】

Design and First-Year Operation of the 50 mgd Membrane Treatment Facility at Gwinnett County, Georgia

机译:格鲁吉亚吉内特县50 MGD膜处理设施的设计和第一年运营

获取原文

摘要

Gwinnett County, located near Atlanta, Georgia, is one of the fastest growing counties in the nation. A new 20 mgd state-of-the-art water reclamation and processing facility, called the F. Wayne Hill Water Resources Center, became operational in December 2000 and now has been expanded increasing its capacity to 60 mgd (maximum month flow basis). The expanded plant produces high-quality water which discharges to the Chattahoochee River downstream of Lake Lanier. When construction of the new discharge line and outfall to Lake Lanier is completed and operational, the treated product water will discharge directly to the lake – the County’s raw water supply source. The NPDES permit for the lake discharge requires the monthly average total phosphorus, ammonia-nitrogen, and turbidity to not exceed 0.08 mg/L P, 0.4 mg/L NH3-N, and 0.5 NTU, respectively. After an extensive 1-year testing period in 2001 and an evaluation of performance, cost, and other factors, membrane filtration using ultrafiltration was selected as part of the advanced treatment processes to treat secondary effluent. The Zenon ZW-500c membrane process was the highest-ranked proposal following a selection process in 2002 that evaluated eight different membrane filtration systems from five manufacturers. Biological processes at the existing (Phase 1) plant were designed for complete nitrification, partial denitrification, and phosphorus reduction. Tertiary treatment processes included ferric chloride chemical coagulation/clarification followed by granular media filters, pre-ozone and granular activated carbon (biologically enhanced activated carbon), and ozone disinfection. The selected process train for the Phase 2 plant expansion treating secondary effluent included: 1. Metal salt coagulant addition/clarification for reduction of phosphorus, organics and solids 2. Screening with drum-type in-channel prefilters 3. Particle filtration with ultrafiltration for turbidity and particle (pathogen) removal 4. Blending with the existing media filter effluent followed by pre-ozone/granular activated carbon for organics removal 5. Final ozonation for disinfection. In the summer of 2002 a three month Membrane System “Proof Test” was started with the ZW- 500c pilot-scale system to confirm design criteria and projected operating costs. Simultaneously, preliminary design commenced incorporating the membrane system into the construction contract documents for the full-scale facility. The UF system consists of 16 parallel process trains with a high degree of redundancy for added reliability. Full production capacity 48 mgd permeate can be met with 14 trains in service and all critical auxiliary equipment and piping are designed for redundancy with backups. Each train has a capacity of 3.6 mgd feed flow and operates at a minimum recovery of 96% at 20 C. The Phase 2 construction began on the AWT (advanced water treatment) facilities in the second quarter of 2003. The testing and commissioning of the first four trains’ 12.5 mgd total capacity began in late 2005. By June 2006, all sixteen trains were operational. This paper will summarize the process design of the membrane facility, start-up activities, and operational data during the first full year of operation. The 50 mgd ultrafiltration system is one of the largest membrane facilities in the world and the largest membrane plant in the Eastern USA.
机译:Gwinnett县位于佐治亚州亚特兰大附近,是全国增长最快的县之一。新的20 MGD最先进的水填写和加工设施,称为F. Wayne Hill水资源中心,于2000年12月开始运营,现在已经扩大了其容量为60 MGD(最大月流量)。扩展植物生产高质量的水,其排放到Lanier湖下游的Chattahoochee河。当建设新的排放线和湖泊湖的排出者完成并运作时,经过处理过的产品水将直接排放到湖泊 - 县的原料供水源。湖排放的NPDES许可证需要每月平均磷,氨 - 氮和浊度,分别不超过0.08mg / L p,0.4mg / L NH 3-N和0.5 NTU。经过2001年广泛的1年试验期并评估性能,成本和其他因素,选择使用超滤的膜过滤作为治疗二级流出物的先进治疗方法的一部分。 Zenon ZW-500C膜过程是2002年选择过程中的最高的提案,其评估了来自五种制造商的八种不同的膜过滤系统。现有(第1阶段)植物的生物方法被设计用于完全硝化,部分脱氮和减少磷。叔处理方法包括氯化铁化学凝固/澄清,然后进行粒状介质过滤器,预臭氧和颗粒状活性炭(生物增强的活性炭)和臭氧消毒。所选的工艺系方法为期植物膨胀处理二级污水:1。金属盐凝固剂加入/澄清磷,有机物和固体的还原2.用滚筒式入口前筛选3.粒子过滤,用浊度超滤和颗粒(病原体)去除4.与现有介质过滤器流出物混合,然后进行臭氧/颗粒活性炭,用于有机物去除5.最终臭氧消毒。在2002年夏天,三个月的膜系统“证明试验”开始使用ZW-500C的试验规模系统,以确认设计标准和预计的运营成本。同时,初步设计开始将膜系统纳入全规模设施的施工合同文件。 UF系统由16个并行过程列车组成,具有高度冗余,以增加可靠性。全生产能力48 MGD渗透物可以满足有14个服务中的火车,所有关键辅助设备和管道都是为备份而设计的。每列火车的容量为3.6 mgd进料流量,在20℃的最低回收率下运行96%。第2阶段建设开始于2003年第二季度的AWT(高级水处理)设施。测试和调试前四列火车12.5 MGD总容量于2005年底开始。到2006年6月,所有十六列车都是运作的。本文将总结膜设施,启动活动和运营期间运营数据的过程设计。 50 Mgd超滤系统是世界上最大的膜设施之一,美国东部最大的膜厂。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号