Case Study-Start-Up and Operation of Deep Rock Connector Tunnel and Pump Station, Indianapolis, Indiana

机译:案例研究 - 深层岩石连接器隧道和泵站的启动和运行,印第安纳州印第安纳波利斯

获取原文

摘要

The Deep Rock Connector Tunnel (DRTC) and Pump Station (PS) were placed into service in December 2017 and March 2018, respectively. The tunneling contractor (JF Shea JV) was responsible for the construction of the tunnel, three CSO diversion structures, and a common Launch/PS Screen and Grit shaft. The pump station contractor (Renda Southland JV) was responsible for constructing a pump station within an underground cavern excavated in rock. This paper will discuss how the work and scheduling challenges were overcome in order to have the facilities in operation by the mandated Consent Decree dates.
机译:深层岩石连接器隧道(DRTC)和泵站(PS)分别于2017年12月和2018年3月投入使用。 隧道承包商(JF SHEA JV)负责隧道,三种CSO引流结构和普通发射/ PS屏幕和砂轴的构造。 泵站承包商(Renda Southland JV)负责在岩石挖掘的地下洞穴内构建泵站。 本文将讨论如何克服工作和调度挑战,以便通过授权同意法令日期进行设施。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号