Removal of old oil filled submarine cables in the Oslo Fjord 2016/2017

机译:删除奥斯陆弗吉斯2016/2017中的旧石油填充潜艇电缆

获取原文

摘要

The Transmission System Operator (TSO) of the Norwegian energy system, completed a new 13 km submarine cable connection across the Oslo Fjord in 2014. The old out-of-service 420 kV submarine oil-filled cables from 1981 was removed in 2016-2017. This paper describes the requirements for the removal project, the project scope, the project execution with engineering, preparation work, removal of the installations and disposal of the cables. The removal project scope consisted of; 70 km of single core 420 kV submarine oil-filled cables at maximum 320 meters water depth in a sailing lane with heavy traffic, removal of oil-pressure systems and termination facilities, recycling of all parts and cable lengths. The project showed that with proper planning and well-prepared procedures, it was managed, together with the chosen contractors, to perform a successful removal and disposal project without any HSE incidents. Due to high metal prices, the project net cost was well within the original budget. The way this removal project was carried out may be to some guidance for other utilities that has old out-of-service oil-filled submarine cables they consider to remove.
机译:挪威能源系统的传输系统操作员(TSO)完成了2014年奥斯陆峡湾的新款13公里的潜水线连接。1981年的旧服务420 kV潜水艇填充电缆于2016-2017 。本文介绍了拆卸项目,项目范围,工程项目的项目执行要求,准备工作,拆除装置和处置。去除项目范围包括; 70公里的单芯420 kV潜水艇填充电缆最多320米水深在帆船巷中,交通繁忙,拆除油压系统和终端设施,回收所有零件和电缆长度。该项目表明,采用适当的规划和准备好的程序,将其与所选择的承包商进行管理,在没有任何HSE事件的情况下执行成功的拆卸和处置项目。由于金属价格高,项目净成本在原有的预算范围内。该拆除项目的实施方式可能是其他公用事业的一些指导,他们考虑删除的旧式溢油潜艇电缆。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号