Urban tunneling through variable geologic conditions―A case study of the Pipeline 3 Relocation Project at State Routes 125/94, San Diego, California

机译:通过可变地质条件的城市隧道 - 在加利福尼亚州圣地亚哥圣地亚哥第125/94号管道3搬迁项目的案例研究

获取原文

摘要

The project consisted of relocating a segment of the San Diego County Water Authority's 66-inch diameter Pipeline 3 to facilitate construction at the State Route 125/94 Interchange by Caltrans. The project had approximately 1,170 feet of tunneled pipeline, 480 feet of cut-and-cover pipeline, three vertical shafts, and two tie-ins to the existing Pipeline 3 at each end of the project. Variable geologic conditions consisted of fractured metavolcanic rock, soft sedimentary rock and unconsolidated sediments, and required several shaft and tunnel excavation and support methods. Project challenges included variable geologic conditions, saturated ground conditions, an urban setting with third party impacts, and an aggressive construction schedule. The greatest technical challenge was tunneling beneath the existing Pipeline 3 with only six feet of cover, with pipeline settlement limited to 1/8-inch.
机译:该项目包括重新迁移San Diego County水务局的66英寸直径管道3的一部分,以便于CALTRAN的第125/94号贸易中的施工。该项目大约有1,170英尺的隧道管道,480英尺的剪切管道,三个垂直轴,以及在项目的每一端的现有管道3中的两个连接。可变地质条件包括骨折的甲状腺岩石,软沉积岩和未覆盖沉积物,以及所需的几轴和隧道开挖和支持方法。项目挑战包括可变地质条件,饱和的地面条件,与第三方影响的城市环境以及积极的施工时间表。最大的技术挑战是在现有的管道3下面的隧穿,只有六英尺的盖子,管道沉降限制为1/8英寸。

著录项

相似文献

  • 外文文献
  • 中文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号