How taking credit for planned and unplanned shutdowns can help you achieve your Safety Integrity Level (SIL) targets

机译:如何掌握计划和无计计划的停机可以帮助您实现安全完整性水平(SIL)目标

获取原文

摘要

Achieving Safety Integrity Level (SIL) targets can be difficult when proof test intervals approach turnaround intervals of five years or more. However, some process units have planned and predictable unplanned shutdowns multiple times a year. During these shutdowns, it may be possible to document that the safety devices functioned properly. This can be incorporated into SIL verification calculations to show that performance targets can now be met without incorporating expensive fault tolerance, online testing schemes, etc. This can result in considerable cost savings for an operating unit.
机译:当验证测试间隔接近五年或更长时间的周转间隔时,实现安全完整性水平(SIL)目标可能很困难。但是,某些过程单位已经计划和可预测的未预期的未预期停机时间一年。在这些停机期间,可以记录适当运行的安全设备。这可以合并到SIL验证计算中,以表明现在可以满足性能目标而不包含昂贵的容错,在线测试方案等。这可能导致操作单元的相当成本节省。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号