TOWN OF OKOTOKS 32ND STREET CROSSING; A MULTIFACETED PROJECT ON THE SHEEP RIVER

机译:Okotoks 32号街道横渡;绵羊河上的多方面项目

获取原文

摘要

The Town of Okotoks' 32nd Street Crossing Project (the Project) involved designing and building a new arterial roadway connecting north and south Okotoks. The Project was completed in 2010 at a cost of $27 M within tight timelines set by the federal Infrastructure Stimulus Fund. The Project included 1.4 km of roadway, bridges over Canadian Pacific Railway (CPR) tracks and the Sheep River, a unique major river realignment, regional pathways, and a long-term channel and aquatic habitat monitoring program. ISL Engineering and Land Services Ltd. led a multi-disciplinary consulting team that included Golder Associates Ltd. who contributed key expertise in river hydraulics, flood management, and aquatic biophysical studies. Early in the design process it was decided to permanently realign a 750 m reach of the Sheep River to a historic river course located approximately 150 m south from the then-current alignment. This innovative idea straightened a meander in the river, reduced river migration potential, and mitigated possible future flood damage to downstream areas. Additional benefits included optimization of functional planning and revising the roadway alignment to a single, large radius curve over both the rail tracks and Sheep River crossings. Aesthetics were also enhanced as the revised Project conforms naturally to the contours and vegetation of the river valley, and provides users with sweeping vistas of the valley and hills beyond. The design included guidebanks to define the bounds of the new river alignment, a guide channel, and fish habitat elements as required by Fisheries and Oceans Canada. In spring 2011, the river experienced a large flood resulting in alterations to bed and bank morphology and realignment of the channel to a more natural course. The Project team, in conjunction with regulators, continues to monitor and evaluate the evolution of this unique Project.
机译:奥科托克斯的32街隧道工程(项目)参与设计和建设一个新的主干道道路连接南北奥科托克斯镇。该项目是在2010年的$ 27男由联邦基础设施刺激基金设定严格的时限内完成的成本。该项目包括公路1.4公里处,在加拿大太平洋铁路(CPR)的轨道和羊河,唯一的主要河流整治,区域通道和长期信道和水生栖息地的监测方案桥梁。 ISL工程和土地服务有限公司领导的多学科的咨询团队,其中包括高达集团有限公司谁贡献河流水力学关键的专业知识,洪水管理,和水生生物物理研究。早在设计过程中,决定永久重新对准羊河的750米达到当然位于150μm左右南从当时的对准的历史性的河流。这种创新的想法拉直在河的曲折,降低河道迁移能力,以及下游地区减轻未来可能出现的洪涝灾害。额外的好处包括功能规划的优化和修改巷道对准在铁轨和羊河口岸既是一个单一的大半径曲线。美学也得到了加强为修订后的项目自然地符合轮廓和河谷植被,并为用户提供席卷山谷的景色和丘陵超越。设计包括guidebanks到所要求的加拿大渔业和海洋定义新河对准,一个引导通道,和鱼类栖息元件的边界。 2011年春天,河水经历导致改建床和银行的形态和渠道的调整,以更自然的过程中大洪水。项目团队,在与监管部门一起,继续监测和评估这个独特的项目的发展。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号