Waterfront Toronto is undertaking a large scale, urban renewal project of the West Don Lands in Toronto, Ontario. As a part of this development, a large flood protection landform was constructed to protect the site from flooding by the Don River, requiring storm water on the site to be redirected to the west. A new storm water outfall was needed to convey this redirected flow out to Lake Ontario. To meet the City of Toronto's 2006 Wet Weather Flow Management Guidelines, storm water needs to be treated before it can be discharged into the environment. The Storm Water Conveyance System (SWCS) project is the first phase of the overall storm water management for the West Don Lands and includes the entire underground infrastructure to manage storm water flow and to allow for a storm water treatment facility that will be built in the second phase of the project. The major components of the SWCS project are two large-scale underground oil grit separators, a vortex drop shaft, deep rock tunnels, an overland flow inlet, a large diameter storage shaft, an overflow structure, and an outfall connection to Lake Ontario. One of the more unique components of the SWCS project was the overflow structure, a large tower in the center of the main shaft that always contains water at lake level and allows storm water to overflow the storage system in large storms and bypass treatment. This structure was built using precast concrete components that were post-tensioned to secure all the segments together. This approach required significant planning and design to ensure that the pre-cast segments were watertight upon completion. This paper discusses the design and construction of the hydraulic structures and components that make up the entire Storm Water Conveyance System for the West Don Lands redevelopment.
机译:Waterfront多伦多在安大略省多伦多的西唐陆地区进行了大规模的城市更新项目。作为这一发展的一部分,建造了一个大型防洪地貌,以保护该部位免受唐河的洪水,需要在网站上进行雨水被重定向到西方。需要一个新的风暴水排出物来将这种重定向流量传达给安大略湖。为了满足多伦多2006年潮湿的天气流动管理指南,需要在将雨水放入环境中进行治疗。雨水输送系统(SWCS)项目是西唐陆地区总体风暴水管理的第一阶段,包括整个地下基础设施来管理风暴水流,并允许雨水处理设施建立在项目的第二阶段。 SWCS项目的主要组成部分是两个大型地下油砂砾分离器,涡流下降轴,深岩隧道,陆上流入口,大直径储存轴,溢流结构以及与安大略湖的出口连接。 SWCS项目的更独特组件之一是溢出结构,主轴中心的大型塔架,总是在湖面上含有水,并允许雨水溢出大型风暴和旁路处理的储存系统。这种结构采用预张紧的混凝土部件构建,该组件被张紧以将所有段固定在一起。这种方法需要重大的规划和设计,以确保在完成后施加预先施加的段是潜水。本文讨论了液压结构的设计和构建,弥补了西唐陆地区的整个雨水输送系统的开发。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号