OCEAN OUTFALL REPAIR TECHNIQUE OFFERS REDUCED RISK AND ECOLOGICAL BENEFITS

机译:Ocean Outfall修复技术提供降低风险和生态效益

获取原文

摘要

The City of Hollywood is responsible for the Hollywood Southern Regional Wastewater Treatment Plant, which is rated at 42 million gallons per day and discharges secondary treated effluent to the Atlantic Ocean via a 60-inch ocean outfall. The outfall is currently the primary method of effluent disposal for the treatment plant. After the passage of Hurricane Andrew in 1992, the outfall required rehabilitation of its cover material over four discrete problem areas comprising a total of approximately 4,000 feet. An articulated concrete mat was chosen at that time to effect repair of the armor covering. Use of the concrete mats offered several advantages over the traditional armor rock, the most notable of which was a more stable cover material that was quicker to install. Adjoining mats were connected together with polyester cable, forming a contiguous repair. The rehabilitation was completed in late 1994. A subsequent inspection of the outfall was performed in May of 1997 to document the integrity of the cover material. At that time, no damage was found to either the original armor rock cover material or the rehabilitated cover material. Because Hurricane Irene, which passed through south Florida on October 15, 1999, caused an estimated $120 million in damage in Miami-Dade County alone, the City of Hollywood conducted another inspection of the outfall in March 2000. The results of the inspection found a substantial amount of the original cover material was missing and that the outfall was visibly exposed in various areas. No visible leaks were found and all exposed pipe appeared to be in good condition. All areas previously repaired with the articulated concrete mat appeared in good condition and exhibited substantial marine growth. Based upon the inspection results, the exposure was not deemed to be extensive and totaled about 82 feet in length. The single largest area in need of repair was approximately 24 feet in length and contained one exposed pipe joint. Options for the extent of repair/rehabilitation were developed and compared as a function of relative risk of continued cover material loss, cost and construction time. Selection of an alternative to implement depended upon available funding and judgment as to the value of the expense versus its corresponding reduced risk. The resistance of the previous repair to storm damage was highlighted.
机译:好莱坞城市负责好莱坞南部区域废水处理厂,每天评分为4200万加仑,通过60英寸的海洋排污场排放大西洋的二次处理过的流出物。该排污目前是治疗厂的流出物种方法的主要方法。在1992年的飓风和鲁沃沃通讯队通过后,排名将其康复物质恢复到四个离散的问题区域,总共约4,000英尺。当时选择铰接式混凝土垫以实现装甲覆盖的修复。使用混凝土垫的使用提供了传统的盔甲岩石的几个优势,最值得注意的是更稳定的覆盖材料,更快地安装。邻接垫与聚酯电缆连接在一起,形成连续修复。该康复于1994年底完成。1997年5月,在1997年5月下进行了随后检查了封面材料的完整性。那时,没有损坏原始装甲岩覆盖材料或康复覆盖材料。由于1999年10月15日通过南佛罗里达州的飓风艾琳造成的迈阿密戴德县损害估计,因此,好莱坞市在2000年3月进行了另一次检查。检查结果发现了缺少大量原始覆盖材料,并且在各个领域明显暴露出口。没有发现可见泄漏,所有暴露的管道似乎状况良好。铰接式混凝土垫以前修复的所有区域出现良好,并呈现大量海洋生长。基于检验结果,暴露未被认为是广泛的,总长度为82英尺。需要修复的单个最大区域的长度约为24英尺,并包含一个暴露的管接头。制定了维修/康复程度的选择,并与持续覆盖材料损失,成本和施工时间的相对风险的函数进行了比较。选择实施的替代方案取决于可用资金和判断费用的价值与其相应的风险降低。突出了先前修复对风暴损伤的抵抗力。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号