Schedule Compression for Construction Projects by Interruption in LOB Scheduling

机译:随着LOB调度中的中断,安排压缩建筑项目

获取原文

摘要

In the line-of-balance (LOB) scheduling, it is necessary that all of the activities are progressed in equal rate of production to establish the schedule as a balanced diagram. In many construction projects, there are one or more activities which progress faster than the other activities. In this paper, interruption of activities with higher production rates and allocation of resources to other activities to decrease the duration of the project is studied. Moreover, the algorithm for calculation of the number of required interruptions, optimal time, project unit for applying interruptions, and the duration of each interruption into suitable activities which the project manager can start earlier is introduced.
机译:在平衡线(LOB)调度中,所有活动都必须以等于的生产率进行,以将计划作为平衡图。在许多建筑项目中,有一个或多个活动比其他活动更快。在本文中,研究了具有更高生产率的活动和资源分配给其他活动,以减少项目持续时间。此外,介绍了计算所需中断数量,最佳时间,项目单元的算法,以及应用中断的持续时间,并介绍了项目管理器更早开始的适当活动。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号