INCREASE IN PRODUCTION BY INCREASING DOUBLE TROUGH OPERATION THROUGH STRAIGHT CAMPAIGN OF TROUGH REPAIR AT G BLAST FURNACE, TATA STEEL JAMSHEDPUR

机译:通过在G高炉,塔塔钢铁棉姆什省通过直接运动通过直接运动,通过直接运动的双槽行动增加生产增加

获取原文

摘要

Non-drainable trough repairs are inevitable in blast furnaces, limiting the drainage facilities. This issue became a bottleneck at G blast furnace leading to a reduction in the production levels. There are two drainable troughs at G Blast furnace with a campaign life of around 160ktons. Two types of repairs are carried out; minor repair after a life of lOOktons and major repair post the trough campaign life. The duration of trough minor repair is around 42 hours and that of trough major repair is around 8 5 hours. As a result, total of 13 major and 13 minor repairs are carried out, thereby resulting in an annual production loss of 17,000 tons. Therefore, to reduce this production loss, various possibilities were explored to lower the frequency of trough repairs, without any compromise in trough health. The paper details out the process followed, resulting in increment in double trough operation by 13 %
机译:在高炉中不可避免的槽维修是不可避免的,限制排水设施。这个问题成为G高炉的瓶颈,导致生产水平降低。 G高炉上有两个可排水槽,竞选寿命约为160ktons。进行两种类型的维修;在寻亮的生活和主要修复后的次要修复岗位展会竞选生活。槽轻微修复的持续时间约为42小时,槽的主要修复约为8小时。结果,进行了13个主要和13个次要维修,从而导致年生产损失为17,000吨。因此,为了减少这种生产损失,探索各种可能性来降低槽维修的频率,没有任何折衷的槽健康。纸张详细介绍了此后的过程,导致双槽操作中的增量13%

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号