首页> 外文会议>International Conference on Fluid Sealing >Achieving a leak free start up- impossible dream or achievable project?
【24h】

Achieving a leak free start up- impossible dream or achievable project?

机译:实现无泄漏启动启动 - 不可能的梦想或可实现的项目?

获取原文

摘要

Large petrochemical plants are shutdown periodically for maintenance and inspection. During the shutdowns a large number of gasketted joints are dismantled in order to gain access to the equipment, and subsequently remade at the end of the shutdown. In order to ensure the integrity of the pressure envelope, the plant Systems are leak tested with high-pressure nitrogen prior to the introduction of hydrocarbons. If leaks from gasketted joints are discovered during this process, it becomes necessary to de-pressure the systems in order that the joints can be remade. During the 1990 Shutdown of the Huntsman Olefins6 plant at Wilton, approximately 200 gasketted joints were required to be re-made during leak testing. This caused significant and costly delays to the start up of the plant. Later analysis showed that the leaks were the result of poor standards in the making and checking of the gasketted joints. A new joint making procedure was written for the 1993 and 1997 shutdowns, and this included a requirement for joints to be traceable by a tagging system to the technician who made the joint. The number of remakes reduced dramatically, to approximately 10 in each of the two shutdowns. In preparation for the 2002 shutdown engineers at Wilton set a target of achieving ZERO remakes during leak testing after the shutdown. This was a great challenge, especially given that approximately 7000 joints were to be remade by 400 technicians. The project was developed in partnership with Hedley Purvis Ltd, who supplied design services for calculating residual bolt loads, and Klinger UK Ltd, who supplied gaskets for use during the shutdown, The Olefins Joint Making procedure was further developed, requiring full traceability and the use of controlled tightening of joints to a pre-defined load. Great emphasis was placed on the role of people in effective joint making, and in ensuring that each technician was carefully briefed and validated in his understanding of the importance to the business of high standards in joint making. A training video was prepared to help in the process of gaining the understanding and involvement of the technicians and their supervisors. Hedley Purvis and Klinger supported Huntsman in the development of the video, and in the delivery of the training and validation exercise. The project was a great success, and resulted in the first "leak free" start up of the Olefins6 plant. The paper will described the project in detail, and will include a showing of the training video.
机译:大型石化植物周期性地关闭进行维护和检查。在停机期间,拆除大量升降的接头以获得对设备的访问,随后在关机结束时重塑。为了确保压力包络的完整性,在引入碳氢化合物之前,植物系统用高压氮测试。如果在该过程中发现来自升降的接头的泄漏,则需要将系统缩小,以使接头可以重塑。在1990年在威尔顿的亨斯曼烯烃6厂关闭期间,需要在泄漏测试期间重新制造大约200个升降的关节。这导致了植物启动的重要且昂贵延迟。以后的分析表明,泄漏是在制作和检查升降的关节方面的标准差的结果。为1993年和1997年关闭编写了一个新的联合制作程序,这包括将标记系统追溯的联合的要求,该技术人员向制定联合的技术人员可追溯。再次减少的再次减少到大约10个关机中的大约10。为准备2002年的威尔顿关机工程师设定了在关闭后在泄漏测试期间实现零重复的目标。这是一个巨大的挑战,特别是考虑到了大约7000个技术人员重塑了大约7000个关节。该项目是与Hedley Purvis Ltd的合作开发的,该LTD提供了为计算剩余螺栓载荷和Klinger UK LTD的设计服务,以及在关机期间提供垫片的供应垫片,烯烃联合制定程序进一步开发,需要满省可追溯性和使用控制接头的紧固到预定载荷。非常重视人们在有效的联合制作中的作用,并确保每位技术员都经过认真介绍并验证他对高标准在联合制作中的重要性。培训视频准备有助于获得技术人员及其主管的理解和参与的过程。 Hedley Purvis和Klinger支持亨斯曼在视频的发展中,并在提供培训和验证练习中。该项目取得了巨大成功,并导致了第一次“无泄漏”启动烯烃6植物。本文将详细描述项目,并将包括培训视频的显示。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号