SUCCESSFUL APPLICATION OF EPB TUNNELING FOR THE DENNY CSO PROJECT, SEATTLE, WASHINGTON

机译:EPB隧道对Denny CSO项目,西雅图,华盛顿的成功应用

获取原文

摘要

A 1.89 km-long, 4.5 m-l.D. tunnel was successfully constructed through saturated hard clay, and highly abrasive dense sand and gravel, with groundwater heads ranging from 10 to 20 m. In order to address these conditions, a Lovat earth pressure balance IBM was used, with soil conditioning by foam, water and various polymers. Support was provided by a single-pass segmented concrete lining. Groundwater inflows of 400 to 1,600 lpm at times created challenges for changing cutting tools. Surface settlements were generally less than measurement thresholds, except under very low cover at startup. This project provides a pivotal case study of the successful application of EPBM technology in saturated, abrasive glacial soils and the successful application of soil conditioners.
机译:1.89公里长,4.5 m-l.d。隧道通过饱和的硬粘土成功构建,高度磨料密集的砂和砾石,地下水头部范围为10至20μm。为了解决这些条件,使用了Lovat地球压力平衡IBM,通过泡沫,水和各种聚合物的土壤调节。通过单通分段混凝土衬里提供支持。地下水流入400至1,600升,有时为改变切割工具创造了挑战。除了在启动时非常低的盖子,表面沉降通常小于测量阈值。该项目提供了枢轴案例研究,对ePBM技术在饱和,磨蚀性冰川土壤中的成功应用以及土壤调理剂的成功应用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号