Significant horizontal and vertical movements were observed in a wharf in Port Melbourne, Australia, soon after its construction. The wharf is about 280m long and was constructed using a sheet pile wall with deadman anchor tie back. About a 70m long downstream section of the wharf exhibited excessive movements indicating failure, which was then stabilised by some immediate remedial work. This paper describes an assessment of the reasons for the failure and further remedial works performed to upgrade the use of the wharf. Stress-deformation analyses, retaining wall analyses and global stability analyses of the wharf were carried out to assess the failure mechanism and also to design the remedial work. The remedial work involved installation of steel tube piles to a deeper depth for the full length of the wharf. Load testing of the wharf was also carried out following the remedial work.
机译:在澳大利亚墨尔本港的码头,施工后不久,在澳大利亚港的码头中观察到显着的水平和垂直运动。码头长约280米,使用带有死亡锚杆的板桩墙建造。大约70米长的码头下游部分表现出过量的运动,表明失败,然后通过一些直接的补救作品稳定。本文介绍了对失败原因的评估以及进行升级使用码头的进一步补救作品。进行应力变形分析,进行码头分析和码头的全局稳定性分析,以评估失效机制,也可以设计补救作品。补救措施涉及将钢管桩安装到更深的深度,为码头的全长。在补救工作之后还进行了码头的负荷测试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号