Cofferdam excavation using soil nail tie-backs for Ocean Park funicular tunnel portal

机译:围堰挖掘围堰挖掘海洋公园缆车隧道门户网站

获取原文

摘要

This paper describes the cofferdam excavation for a tunnel portal to facilitate construction of a new funicular tunnel as part of the redevelopment of Ocean Park. The portal wall was supported by pipe pile wall with soil nail tie-backs instead of ground anchors proposed by the reference design. As the design was jointly developed with the Contractor, it is able to address a number of constructability issues to suit the Contractor’s particular method of construction. Construction of the tunnel portal was particularly challenging as it involved working within very restricted land boundaries and works were carried out as the theme park remained open to visitors. Various instrumentation and monitoring works were carried out to ensure safety of the works and public. The final part of the paper compares the measured settlement against the design predictions, following completion of the excavation and temporary support works. The revised design was able to provide substantial savings, both in terms of construction time and cost, as the original reference design using ground anchors would have required a longer installation time and a more comprehensive set of performance tests.
机译:本文介绍了隧道门户网站的围堰挖掘,以便于建造新的缆道隧道作为海洋公园重建的一部分。门墙由管桩墙支撑,带有土着钉架而不是参考设计提出的地锚。随着该设计与承包商共同开发,它能够解决许多建设性问题,以适应承包商的特定建设方法。隧道门户的建设尤其具有挑战性,因为它涉及在非常受限制的土地边界内工作,因为主题公园对游客仍然开放。进行了各种仪表和监测工程,以确保工程和公众的安全性。在完成挖掘和临时支持工作之后,本文的最后一部分比较了对设计预测的测量结算。修订后的设计能够在施工时间和成本方面提供大量节省,因为使用地锚的原始参考设计将需要更长的安装时间和更全面的性能测试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号