A clay-capping trial was established in 1996 on Magazine Dump at the Mt Lyell Copper Mine. The trial was initially constructed under the Mount Lyell Remediation Research and Demonstration Program, a co-operative venture between the State and Federal governments. The detailed engineering design for the clay cover included the following features; reshaping and compaction of dump batters, 5 m vertical bench interval, overall side-slopes of 2.5:1, emplacement of clay in four 150 mm lifts, compaction by a 10 t vibrating roller or 'track rolling' on batters with density testing for quality control. A small section at the base of the dump (<10 per cent of dump surface area) was not capped. The dump was instrumented with seven 20 m deep temperature and oxygen probe holes. Six lysimeter drums were installed under the cover. Leachate from the dump passes through a single, continuously monitored gauging weir. Five years after construction, the clay cover exhibits a high degree of moisture saturation. The lysimeter data suggest that infiltration into the dump through the well-compacted dump plateaux is approximately ten per cent of precipitation. Conductivity flux emanating from the dump shows a very gradual decreasing trend and the autumn pollutant flush events are much diminished. These findings are consistent with a successful Temperate Zone capping project. The trial also generated certain unexpected findings. Field permeability tests on the cover yielded uncertain results and oxygen remains available throughout the dump. The flow data indicate that, while total outflow has decreased as a result of storm shedding, inputs from groundwater and batter infiltration are still significant. Outflow during the driest weeks of the year may have risen following capping. Detailed assessment of the data is hampered by insufficient pre-capping information; however, there is a possibility that conductivity flux emitted when flows in the receiving environment are at their annual minimum is unchanged or worse post-capping.
机译:1996年在MT Lyell铜矿的杂志垃圾上成立了粘土封盖试验。该试验最初根据莱尔修复研究和示范计划,国家和联邦政府之间的合作开展企业建设。粘土盖的详细工程设计包括以下功能;重塑和压实倾卸击球,5米垂直台间隔,总侧斜坡为2.5:1,粘土施加在四个150毫米升降机中,压实10 T振动滚筒或“轨道滚动”,具有密度检测质量的密度测试控制。倾倒底部的小部分(<10%的倾倒表面积)未加盖。垃圾箱有七个20米温度和氧气探头孔。在盖子下安装了六个立体计鼓。从卸纸的渗滤液通过单一连续监测的测量堰。施工五年后,粘土罩显示出高度的水分饱和度。 Lysimeter数据表明,通过良好压实的倾倒平原渗透到倾卸大约是降水量的约10%。从倾卸发出的电导率助焊剂显示出非常逐渐逐渐降低的趋势,秋季污染物冲洗事件大大减少。这些发现与成功的温带区域封盖项目一致。该试验还产生了某些意外的发现。盖子上的现场渗透性测试产生不确定的结果,氧气仍然可用。流量数据表明,虽然由于风暴脱落而总流出量减少,但地下水和面糊渗透的输入仍然很大。在一年中最干燥的星期内的流出可能会在封盖后升起。通过预封盖信息不足,对数据的详细评估受到阻碍;然而,在接收环境中流动时,电导率通量可能在其年度最小值中不变或更糟糕的后封锁。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号