Snorre B Project - Contract Strategies and Project Execution

机译:Snorre B项目 - 合同策略和项目执行

获取原文

摘要

This paper focuses on the contract strategy and project execution and the final result of the Snorre B project, located in the Tampen area of the Norwegian continental shelf. The project comprise a semisubmersible production platform with full drilling facilities, subsea development for 26 wells, gas export/Import facilities and oil export to Statfjord B for storage and offloading. The principle behind the contract strategy was that the contractors should tender a product developed inhouse instead of being forced to bid on a product developed by the oil company through a study phase. The contracts were signed in April 1998 and production start was June 27, 2001 which was 2 months ahead of schedule.
机译:本文重点介绍了合同战略和项目执行以及位于挪威大陆架的坦布地区的Snorre B项目的最终结果。该项目包括一个具有完整钻井设施的半熟型生产平台,26个井的海底开发,天然气出口/进口设施和石油出口到Statfjord B,用于存储和卸载。合同战略背后的原则是承包商应投标产品,而不是被迫通过研究阶段向石油公司开发的产品投标。合同于1998年4月签署,2001年6月27日的生产开始于2001年6月27日提前2个月。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号