SHOREHAM DECOMMISSIONING AND LICENSE TERMINATION - A SUCCESS STORY

机译:Shoreham退役和许可证终止 - 成功的故事

获取原文

摘要

In April 1995, the United States Nuclear Regulatory Commission (NRC) issued an Order terminating the Shoreham Nuclear Power Station's license and authorizing the unrestricted release of the Shoreham facility. The receipt of the License Termination Order was the culmination of a seven-year long licensing effort supported by extensive studies, detailed cost and schedule evaluations and the successful implementation of the NRC-approved Decommissioning Plan. Shoreham was the first large, NRC-licensed, commercial nuclear power plant to achieve the final goal of license termination. The pioneering nature of the project made the Shoreham experience unique and challenging in many ways. The lack of previous experience with the new decommissioning rule, gaps and ambiguities in the regulations and the absence of well-established procedures and guidelines inevitably led to regulatory uncertainties and delays. In spite of the delays imposed by the licensing process, the decommissioning of the Shoreham plant proceeded with remarkable speed and efficiency. Innovative approaches were employed to tackle difficult regulatory and technical issues. Shoreham decommissioning was completed ahead of schedule and within budget. Close communication with the NRC Staff throughout the project was an essential element in the success of the Shoreham decommissioning project. This enabled prompt identification of potential regulatory issues and their early resolution. The NRC regulations do not treat spent fuel disposal as a decommissioning activity, nor is the cost of fuel removal and disposal included in the decommissioning cost estimate. Fuel disposal is considered to be an operational activity. It is, however, necessary to remove the fuel from the spent fuel storage pool before the pool and the associated systems can be decontaminated and the facility released for unrestricted use. Therefore, the disposal of the slightly irradiated Shoreham fuel was critical to the success of the Shoreham decommissioning project. After developing many different disposal options (reuse, reprocessing and storage) and overcoming legal challenges reaching all the way to the United States Supreme Court, transfer of the Shoreham fuel assemblies to the Limerick nuclear power station for reuse was completed in June 1994, three months ahead of schedule. The insight gained from the Shoreham experience is paving the way for better decommissioning regulations and guidelines from the NRC, particularly as they apply to prematurely shut down plants. The NRC is attempting to examine the problems, determine the causes and come up with solutions in the form of changes to decommissioning regulations. The regulatory changes, clarifications and guidance resulting from this effort are sure to help future decommissioning projects by establishing a more predictable regulatory regime. As the Shoreham decommissioning project came to a successful conclusion, it became evident that the benefits flowing from the project were not confined to the licensing and regulatory arena. It contributed significantly to the knowledge base in such areas as decontamination and dismantling methods, control of personnel radiation exposure, termination survey techniques, spent fuel transportation and public relations. Shoreham also convincingly demonstrated that the cost and schedule of a large, complex decommissioning project are predictable.
机译:1995年4月,美国核管理委员会(NRC)发出命令终止肖勒姆核电站的许可证和授权肖勒姆设施的无限制释放。在收到许可终止命令是通过广泛的研究,详细的成本和进度的评价,并成功实施了NRC批准的退役计划的支持七年的龙牌工作的高潮。肖勒姆是第一大,NRC授权,商用核电站,实现许可终止的最终目标。该项目的先锋队性质作出肖勒姆经验独特,在许多方面都具有挑战性。缺乏与条例的新规则退役,差距和模糊和缺乏行之有效的程序,不可避免地导致了监管的不确定性和延误的指导方针的经验。尽管发牌过程中造成的延误,在肖雷汉姆核电厂的关闭进行了显着的速度和效率。创新的方法被用来解决困难的监管和技术问题。肖勒姆退役被提前预算内进度完成。在整个项目的NRC工作人员密切沟通是在肖勒姆退役项目取得成功的一个重要因素。潜在的监管问题这使得迅速识别和他们早日解决。 NRC的法规不把乏燃料处置作为一个退役的活动,也不是燃料清除和处置列入退役成本估算的成本。燃料处置被认为是一个业务活动。然而,有必要从乏燃料存储池取出燃料前池以及相关的系统可以净化和发布无限制使用的设施。因此,稍有照射肖雷汉姆燃料的处置是对肖勒姆退役项目成功的关键。开发不同的处理方式(再利用,再加工和存储),克服达到所有的方式向美国最高法院的法律挑战后,肖勒姆燃料组件,以供重新使用利默里克核电站的转让在1994年6月三个月完成提前于计划。从肖勒姆经验获得的洞察力铺平了更好的退役规章和准则从NRC,特别是因为它们适用于过早地关闭工厂的方式。核管理委员会正在试图研究的问题,确定原因,并提出了在改变退役法规的形式解决方案。监管的变化,澄清,并从这种努力产生指导一定会帮助未来建立一个更可预测的监管制度退役项目。由于肖勒姆退役项目圆满结束,很明显,从项目流动的好处并没有局限在许可和监管领域。它显著贡献等方面的去污和拆除方法,人员辐射照射的控制,终止调查技术,乏燃料运输和公共关系的知识基础。肖勒姆也令人信服地证明了一个庞大,复杂的退役项目的成本和进度是可以预见的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号